It seems that estimating the cost
of school construction projects is like aiming at a moving target—a
target that keeps getting higher.
Iredell County and the
Iredell-Statesville Schools retained Construction Control Corporation to
evaluate the construction projects recommended by the Joint Facility
Task Force.
Construction Control presented its
findings February 15. The cost of the projects in Phase One of the plan
was estimated at $116,893,129. School officials had put a price tag of a
little over $80,000,000 on the same projects.
The consultant’s report explained
that in 2004 construction prices had increased about 15 per cent, well
above the normal increase of about four percent per year. This rise in
construction costs does not come close to accounting for the overall 45
percent increase in the price of the projects.
The report stated: “Our review
identifies all work that we believe necessary to bring a building up to
a level which we would consider very good to excellent condition. This
level is maintained at each school so that all schools are as equal as
possible.”
The most expensive Phase One
project is Statesville High School. The Facility Task Force had
recommended that the existing buildings be renovated and a freshman
academy added. At various times school officials estimated the cost of
this project at $16 to $21 million.
Construction Control recommended
that the existing buildings at the school be demolished and replaced
with a new structure, at an estimated cost of $39,959,850.
Task Force had called for closing
Monticello elementary school and transferring its students to an
expanded N.B. Mills. The consultants recommended that both schools be
closed and replaced with a new building estimated to cost $11,794,781.
It would require a substantial tax
increase to finance the recommended projects any time in the near
future.
|
Statesville High School New School |
39,959,850 |
|
West Iredell High School Renovations &
Additions |
13,348,324 |
|
N.B. Mills & Monticello Replace with new
school |
11,794,781 |
|
Mount Mourne Elementary New School |
11,794,781 |
|
Troutman Elementary Renovations &
Additions |
9,056,225 |
|
Sharon Elementary School Renovations &
Additions |
5,830,601 |
|
West Iredell Middle School Renovations &
Additions |
5,004,145 |
|
Troutman Middle School Renovations &
Additions |
4,876,939 |
|
Lake Norman High School Additions only |
4,856,088 |
|
Brawley Middle School Renovations &
Additions |
4,690,140 |
|
North Iredell Middle School Renovations
& Additions |
4,385,389 |
|
Statesville Middle School Renovations
only |
1,295,866 |
|
Total Phase One |
$ 116,893,129 |